How Long Does Planning Permission Take? Realistic Timelines
Planning application timelines, 8-week targets, pre-application advice, conditions, and the real-world total time from idea to completion.
Planning application timelines, 8-week targets, pre-application advice, conditions, and the real-world total time from idea to completion.

One of the most common questions homeowners ask: "How long will planning take?"
The answer most architects give is "8 to 13 weeks." That's technically correct - but it's incomplete. It's the decision time, not the total time. The real timeline from "I have an idea" to "work is finished" is much longer.
Here's the reality.
These are the statutory decision times set by the Planning and Compulsory Purchase Act:
This is the time for the council to review your application, consult neighbours, and issue a decision.
Important: This clock starts after you submit a valid application - not before.Here's what actually happens from start to finish:
Before you apply officially, you'll usually submit drawings to the council for informal feedback. This costs £100–300 and takes 2–4 weeks.
The pre-app achieves two things:
This step is not mandatory but is almost always worth doing. It saves time and money later.
Total time so far: 4–8 weeks (including back-and-forth)After pre-app feedback, your architect or planning consultant refines the drawings and prepares the planning statement. This is the detailed document explaining why your proposal fits planning policy.
For complex projects (listed buildings, conservation areas, major extensions), this takes longer. For straightforward rear extensions, it's quicker.
Total time so far: 8–18 weeksYou submit the application to the council with all required documents. The council does a validation check to confirm everything is included. If something is missing, they ask you to resubmit (add 1–2 weeks).
Total time so far: 9–19 weeksThe council reviews the application. The clock runs for 8 weeks (13 for major applications).
What happens during this time:
Planning permission rarely comes with zero conditions. Common conditions include:
You have to submit evidence that conditions are met before you can start work. Some councils are quick at approving these; others take weeks.
Total time so far: 19–40 weeks (4.5–9 months)Once you have planning permission, you apply for Building Regs approval. This covers structural safety, energy efficiency, fire safety, etc.
The council Building Control team reviews structural drawings and specifications. They usually approve within 2–4 weeks.
Total time so far: 21–44 weeks (5–10 months)Once work is finished, a Building Control inspector visits to confirm the work meets regs. They sign off the completion certificate.
Total time from start to finish: 22–46 weeks (5–11 months)If your project is complex or contentious, add more time:
A contested planning application in a conservation area can take 6–12 months just to get permission, before you even start Building Regs.
1. Do pre-app advice properly – Get council feedback before you invest in full drawings. This catches issues early.
2. Hire an experienced planning consultant – They know your council and can anticipate objections. Worth £1,000–2,000 to save 4–8 weeks.
3. Avoid peak periods – Summer (July–August) and holidays slow councils. Submit in spring or autumn if you can.
4. Design within policy from the start – If your scheme clearly fits local planning policy, there's less to argue about and fewer delays.
5. Respond quickly to council queries – If they ask for information, send it within 48 hours. Delays on your end extend everything.
6. Minimise conditions – During pre-app, ask what conditions are likely. Design to avoid them if possible.
7. Don't use agents or planners who are slow – Choose people with a good track record in your council area.
Once you have planning permission, you have 3 years to start work before the permission expires. Once work has "commenced" (which can mean almost anything - digging a foundation, placing a materials skip, etc.), the permission is "live."
But this doesn't mean you should rush. Many people get permission and don't build for 1–2 years. That's fine, as long as you've started something.
Planning permission takes 5–11 months for straightforward projects. For complex or contested projects, it can take 12–18 months or longer.
If you're planning a home improvement:
The councils aren't slow to be difficult - they're just under-resourced and every application takes time.
---
Want to understand the timeline for your specific project? Use PlanCheck to assess your property, understand what application type you'll need, and get realistic timings for your local council. Check your project now.Get instant clarity on planning permission for your specific project and location.
Start your assessmentTwo-storey extension permitted development rules, when planning permission is required, and realistic costs and timelines.
Read →Conservation area planning rules, what's restricted, what still counts as permitted development, and how to get approval.
Read →Garden rooms, garden offices, summer houses - when you need planning permission and the permitted development rules that apply.
Read →